The Hanslope Junction Renewal Project was a major track upgrade and renewal on the West Coast Main Line, led by Network Rail as the infrastructure owner and client, with delivery coordinated through the Central Rail Systems Alliance (CRSA) — a partnership between Network Rail, Balfour Beatty, AtkinsRéalis and TSO. Network Rail planned and funded the £26 million overhaul of the junction, which involved replacing track panels, renewing ballast and upgrading Switches and Crossings (S&C) to improve reliability and long‑term performance on a key section of the UK rail network.
Swietelsky UK played a key part in the delivery of this major project, working on behalf of Network Rail and the CRSA. At peak delivery, up to 70 Swietelsky UK personnel were involved across planning, operations, supervision and delivery roles, reflecting the scale of commitment and collaboration required.
A key component of this success was the deployment of all four SB Rail Kirow KRC 250 cranes, which worked around the clock to install the highly complex track layout. The cranes lifted and positioned large, prefabricated track panels precisely into place across all four lines of the formation. The Kirow crane team’s professionalism, commitment and technical expertise ensured that all panels were installed safely and efficiently with zero operational issues. Their contribution demonstrates Swietelsky UK’s ability to manage highly demanding lifting and installation operations with precision and reliability.
Equally important was the role of Swietelsky UK’s On‑Track Machine (OTM) capability, including the specialist teams responsible for planning, operating and supervising the plant on site. Four Swietelsky UK Plasser & Theurer 09‑4x4/4S Dynamic tampers were used on the project, undertaking tandem tamping through the S&C formations and applying dynamic track stabilisation to deliver the highest possible track quality standards. This ensured the route was handed back at line speed, as required.
Through detailed possession planning, close coordination with the Kirow operations and constant on‑site oversight, the OTM teams ensured seamless integration with wider site activities. Their expertise was critical in maintaining safety, compliance and operational efficiency throughout every phase of the work.
The Hanslope Junction renewal project is particularly noteworthy for its scale, technical demands and operational complexity. These works were also carried out over the festive period, while many others were enjoying holidays and celebrations. Successfully completing the project on time underscores the skill, dedication and teamwork of everyone involved. It exemplifies Swietelsky UK’s technical excellence, operational capability and commitment to delivering high‑quality railway infrastructure solutions. It also highlights the synergy between lifting specialists, OTM support and workshop teams — a demonstration of the company’s slogan #BuildingEverBetter in practice. This achievement would not have been possible without the commitment and professionalism of Swietelsky UK’s machine crews, supervisors and managers, whose hard work, teamwork and dedication were at the heart of the company’s success on the project.









